Analysis and Application of Construction Management in The Waled-Ciledug BTS Road Reconstruction Project
DOI:
https://doi.org/10.46799/jst.v6i2.1065Keywords:
CPM, PERT, Project ControlAbstract
Project planning, cost, time, quality, contract administration, and safety management are the regulated aspects of construction in construction management. As a result, project objectives cannot be realized without competent construction management. Planning, execution, and control are the three main functions of construction management. All human and other project resources are managed through these three processes: planning, execution, and review. The purpose of this study aims to determine construction time management, find out how long the project duration will take if using CPM and PERT methods, analyze CPM and PERT on the comparison of planning time. The approach method used is a qualitative technique that involves collecting field data that will be used as information for the research topic. The researcher uses the CPM and PERT methods as a tool in projects related to a management in planning and control in the project. The CPM and PERT methods are used to figure out the duration of the project required and also identify the types of critical work in the project. Based on the analysis conducted, the CPM method only requires 100 days and the PERT method 100.48 days. Using the CPM method produces a time efficiency of up to 20 days compared to the PERT method of only 19.52 days. From the results obtained, the critical path of the two methods is A, B, C, D, and also the non-critical path is E, the duration is faster than the previous plan schedule which is 120 days.
Downloads
References
Adekunle, P., Aigbavboa, C., Akinradewo, O., Oke, A., & Aghimien, D. (2022). Construction Information Management: Benefits to the Construction Industry. Sustainability (Switzerland), 14(18). https://doi.org/10.3390/su141811366
Astika, I. B. P., & Dwirandra, A. (2020). Information technology duty, satisfaction and ais effectiveness moderate effect of benefits of informs technology on employee performance. International Research Journal of Management, IT and Social Sciences, 7(6), 9–20.
Boonpheng, A., Kongsong, W., Kongbenjapuch, K., Pooworakulchai, C., Harnphanich, B., & Roikulcharoen, S. (2021). Using Blockchain Technology and Cryptocurrency for Contract Management in Construction Engineering. International Journal of Management (IJM), 12(2).
Bradley, D., Merrifield, M., Miller, K. M., Lomonico, S., Wilson, J. R., & Gleason, M. G. (2019). Opportunities to improve fisheries management through innovative technology and advanced data systems. Fish and Fisheries, 20(3), 564–583.
Farida, Yuniar, & Lulitasari Putri Anenda. (2022). Network planning analysis on road construction projects by CV. X using evaluation review technique (pert)-critical path method (CPM) and crashing method. Nternational Journal of Integrated Engineering 14.4, 4, 377–390.
Levy, & Sidney M. (2002). Project management in construction.
Navimipour, N. J., & Soltani, Z. (2016). The impact of cost, technology acceptance and employees’ satisfaction on the effectiveness of the electronic customer relationship management systems. Computers in Human Behavior, 55, 1052–1066.
Nisarg Arvindbhai, S., & Solanki, J. V. (2020). Applying Concept of Operational Research in Construction Industry. International Research Journal of Engineering and Technology.
Nurhikmah, N. (2024). EDUCATIONAL MANAGEMENT FUNCTIONS: PLANNING, ORGANIZING, ACTUATING, CONTROLLING. INTIHA: Islamic Education Journal, 1(2), 82–91. https://doi.org/10.58988/intiha.v1i2.293
Onana, J.-C. (2018). Factors Affecting the Performance of Contractors on Road Projects Supervised by the National Agency of Public Works in Gabon. In Journal of Materials Processing Technology (Vol. 1, Issue 1).
Trietsch, D., & Baker, K. R. (2012). PERT 21: Fitting PERT/CPM for use in the 21st century. International Journal of Project Management, 30(4), 490–502. https://doi.org/10.1016/j.ijproman.2011.09.004
Winch GM., & John Wiley & Sons. (2012). Managing construction projects.
Yan, M.-R., Chien, K.-M., & Yang, T.-N. (2016). Green component procurement collaboration for improving supply chain management in the high technology industries: A case study from the systems perspective. Sustainability, 8(2), 105.
Zhang, M., Cao, T., & Zhao, X. (2017). Applying Sensor-Based Technology to Improve Construction Safety Management. Sensors, 17(8), 1841. https://doi.org/10.3390/s17081841
Downloads
Published
Issue
Section
License
Copyright (c) 2025 Radja Syahidir Firdaus, Herry Hermawan

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International.
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution-ShareAlike 4.0 International (CC-BY-SA). that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work.